Construction Project Budget Template

A project budget breaks the contract into cost heads and tracks budget, committed (orders placed) and actual cost. The variance column shows overruns before they eat the margin.

Free, no sign-up. Works in Excel, Google Sheets and LibreOffice. Columns marked “auto” are formulas.

Preview

Cost codeCost headBudget (₹)Committed (₹)Actual to date (₹)Balance (₹)% used
MAT-01Cement, steel and aggregates1,80,00,0001,45,00,0001,12,00,000autoauto
MAT-02Finishing materials45,00,00012,00,0004,00,000autoauto
LAB-01Labour — direct90,00,000051,00,000autoauto
SUB-01Subcontract — MEP65,00,00065,00,00023,00,000autoauto
EQP-01Equipment hire and fuel25,00,0009,00,00013,50,000autoauto
OVH-01Site overheads20,00,000011,00,000autoauto

How to use this template

  • Balance uses the higher of committed and actual so open orders count against the budget.
  • Review weekly alongside progress — % cost used should track % work done.